FERC reschedules final Environmental Impact Study on the PennEast Pipeline

Dallas Post · January 23, 2017

The Federal Energy Regulatory Commission will extend the completion date deadline for the final environmental impact statement for the PennEast Pipeline project, according to a news release dated Jan. 23.

The revised date would change the Feb. 17 final EIS due date to April 7 and give FERC until July 6, 2017, to make a final decision on the planned 120-mile natural gas pipeline.

The PennEast Pipeline will start in Dallas Township and transport up to one billion cubic feet of Marcellus Shale natural gas to a Transco pipeline connection in Mercer County, New Jersey.

“Due to additional environmental information filed by PennEast and certain state agencies since the issuance of November 8, 2016, Scheduling Notice, the Commission staff requires more time to analyze all the environmental data and prepare the final EIS,” FERC’s news release stated.

In a separate news release, the PennEast Pipeline Company said it supports FERC’s final EIS extension.

“After a two-and-a-half year review of PennEast Pipeline Company’s application, including 33 route adjustments announced in September to further reduce environmental impact, the additional 49-day review period FERC announced today will help ensure a complete and thorough review,” Pat Kornick, spokesperson for PennEast Pipeline Company said in the news release. “PennEast looks forward to receiving the final EIS and anticipates the line will be operational in the second half 2018.”

In September 2016, PennEast developed 33 pipeline route deviations to comply with FERC’s recommendations to reduce impacts on endangered species and wetlands and make better usage of existing utility rights of way.

“FERC determined in its initial environmental assessment that the PennEast Pipeline would have minimal environmental impact and could even improve the region’s air quality as natural gas displaces other less clean fuels for electric power generation,” Kornick said in the news release. “PennEast is confident the Project can be built safely and with minimal environmental impact and will continue to provide necessary data as FERC continues its due diligence on the project.”

Web1 PennEast Pipeline logo 1

/wp-content/uploads/2017/01/web1_PennEast-Pipeline-logo-1.jpg

By Eileen Godin

egodin@timesleader.com

Reach Eileen Godin at 570-991-6387 or on Twitter @TLNews.